BNW

 

Biafra Nigeria World News & Archives

 

BNW News and Archives

 

 

BNW: the Authority on BiafraNigeria

BNW Magazine 

Biafra Nigeria World Forums and Message Board

 BNW News Archive

BNW Home

 

BNW Writer's Block

 WaZoBia @ BNW

Biafra Net

 Igbo Net

Africa World and BNW Africa 

Submit Article for Publication

BiafraNigeria Spacer

BiafraNigeria Spacer

 

Flag of Biafra Nigeria

 

BNW News Archives

BNW News Archive 2002-January 2005

BNW News Archive 2005

BNW News Archive 2005 and Later

 

BiafraNigeriaWorld News: Weblogs Edition @ Blog Continent


« EFCC denies probe of Balogun’s sureties | Main | May Day tragedy: 15 killed in auto crash »

May 03, 2005

Why Owerri-Yenagoa power line is delayed–– Firm

PIVOT Engineering Limited, the contractor handling the $76 million (N10.1 billion) Owerri-Ahoada-Yenagoa 132kv transmission line has attributed delay in the completion of work on the project to major adjustments on the original design by the federal government.

KAYODE EKUNDAYO, Asst Business Editor

Ministry of Power and Steel and National Electric Power Authority (NEPA) had awarded the construction of a single phase 132 kv transmission line of $56 million (N7.4 billion) to Pivot Engineering in November 2000. The project was to be completed within 72 months of the contract award and was designed to stretch from Owerri in Imo State to Yenagoa, Bayelsa State.

Though construction work is still ongoing, Pivot Engineering Executive Director (Business) Mr. Olusegun Ahmadu attributed the delay to adjustments in the original design as well as community problems which also led to the upward review of the contract sum from $56 million to $76 million.

According to Ahmadu in a recent interview with Daily Champion said the original contract was to construct 132kv single circuit line from Owerri and step down at Ahoada to improve supply in the area and then move to Yenagoa.

"But in the course of approval, the Federal Government decided to tee-off from Ahoada to Abonema, also construction of new 40 mva, 132/33kv substation at Imiringi as well as inclusion of 132 kv double circuit line from Owerri to Yenagoa. All these were not in the original design.

Ahmadu explained that the situation was further aggravated by community agitations and disturbance which resulted in kidnapping of site engineers as well as seizure of construction equipment and damage to same by youths.

"We have to abandon the site for sometime. On intervention, we were told that they would not allow us to return to work until we agree with some terms," he said.

Nevertheless, Ahmadu said, work on the project has reached an advance stage and by December 31, Yenagoa would be lighted up.

He said the company has finished the segment of work from Owerri to Ahoada "so much so that there is power supply in Ahoada since December 2004" Ahmadu said.

Although, the main target is to link up Yenagoa to the national grid, Ahmadu said since electricity has reached Ahoada, it would not take too much time to finish the main assignment.

"Our major challenge has been pilling in swampy areas . But I can assure you that transmission line to Yenagoa is 80 per cent ready including the substation. Precisely by June, the station will be ready. Besides, pilling, poles erection is about 80 per cent completed," the executive director said.

Posted by Publisher at May 3, 2005 09:08 AM

Comments

Post a comment

Thanks for signing in, . Now you can comment. (sign out)

(If you haven't left a comment here before, you may need to be approved by the site owner before your comment will appear. Until then, it won't appear on the entry. Thanks for waiting.)


Remember me?





BNW Writers A-M


BNW Writers N-Z

 

BiafraNigeria Banner

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

 

BiafraNigeria Spacer

BiafraNigeria Spacer

 

BNW Forums

 

The Voice of a New Generation